Traffic problems for Pattaya Tai until the end of the year

Post by Gaybutton »

Half of Pattaya South Road closed until year-end

By Pattaya Mail

June 11, 2020

South Road will be reduced to one-way traffic from June 13 until the end of the year as part of the Provincial Electricity Authority’s project to bury power lines.

Eastbound traffic will be prohibited from Third Road to Sukhumvit Road, with the right lane closed to improve the electrical system in preparation to relocation of electricity cables and communications lines.

Detour signs went up June 9 and people are advised to find other routes to access Sukhumvit Road until the end of the year.

For more information call 087-230-8118.

https://www.pattayamail.com/featured/ha ... end-303662

See also: https://www.gaybuttonthai.com/viewtopic.php?f=3&t=10391

User avatar
Gaybutton
Posts: 17603
Joined: Sat Jul 31, 2010 11:21 am
Location: Thailand
Has thanked: 2 times
Been thanked: 897 times

Re: Traffic problems for Pattaya Tai until the end of the year

Post by Gaybutton »

Major South Pattaya Road construction begins, six month timeframe of a one way road expected

By Adam Judd

Tuesday, 16 June 2020

A significant road construction project has begun this week which will limit traffic to one way on South Pattaya Road for an estimated six months to support an underground cabling project in South Pattaya.

Pattaya City Deputy Mayor Kietisak Sriwongchai along with Major Arut Sapanon from the Pattaya City Traffic Police inspected the construction area on South Pattaya Road yesterday afternoon.

Major Arut told The Pattaya News “More traffic police are being assigned to patrol near the construction area to prevent vehicles from stopping on the yellow white and red lines in the construction zones, as well as cutting through the overall construction area on South Pattaya Road.”

“No parking signs are placed along Pattaya Third Road around the vicinity of the construction entrances to South Pattaya Road.” Major Arut added.

“Road construction signs and lights are placed on the construction area overall throughout South Pattaya Road to make sure that road users will clearly see and avoid any accidents.” Major Arut concluded.

The construction project manager, Mr. Thanoo Surachailikawit told The Pattaya News “The road construction for underground cable and wire line installation is going to take about six months.”

Story and photos: https://thepattayanews.com/2020/06/16/m ... -expected/